 Jalan Layang Semanggi Selesai Agustus 2017

Semanggi Elevated Road to Finish in August 2017

Jakarta Dept. of Bina Marga targets to finish Semanggi elevated road construction in 18 months. The construction is started on Friday (4/8) and to complete in August 2017. It is hoped the elevated road would able to decrease traffic jam.

Our target is completed in August 2017

Yusmada Faizal, Jakarta Head Dept. of Bina Marga, explained the project takes 540 calendar days including 60 days of planning and 480 days of construction.

“Our target is completed in August 2017,” he said, Friday (4/8).

Semanggi Interchange Project Begins

The elevated road projects are detail engineering design (DED), preparation, loop shifting, construction implementation, and drainage as well as traffic sign.

Two elevated road will be built. First is from Grogol to Blok M direction by 796 meters and Polda to Monas direction by 826 meters.

Linked News
Popular News indeks
  1. BMKG: Sunny to Cloudy Skies Forecast Across Jakarta Today

    access_time11-09-2026 remove_red_eye1700 personDessy Suciati
  2. Jakarta Reallocates Funds for Rp 250M Suckermouth Catfish Study After Pramono’s Direct Order

    access_time10-09-2026 remove_red_eye696 personFakhrizal Fakhri
  3. Pramono Urges Jakmania to Keep Jakarta Safe

    access_time11-09-2026 remove_red_eye454 personDessy Suciati
  4. Pramono Endorses Five-City Tour for Jazz Goes to Campus

    access_time12-09-2026 remove_red_eye429 personDessy Suciati
  5. No Damage Reported Following Magnitude 5.9 Seribu Islands Quake

    access_time12-09-2026 remove_red_eye418 personBudhi Firmansyah Surapati